Upload and distribute a new drawing revision

v2026.3 · Updated 15 Sep 2026 · 6 min read

Every controlled drawing in SasCon keeps a revision history. When you upload a new revision it supersedes the previous one, the audit trail stays intact, and everyone on the distribution matrix is told. This article takes you through it twice over: first the upload, then the distribution.

Before you start

Where you do this
Documents → Register
You will need
The signed-off drawing file, and the revision letter from its title block
Takes about
Five minutes, plus review time
You need one of these roles:Document controllerProject administratorConsultants and sub-contractors can view the result, not publish it.
Walkthrough video not uploaded yet
Walkthrough · 4:12
Watch it done — 4:12 walkthrough. Prefer reading? The written steps below cover the same ground.
  • 0:00Opening the register
  • 1:20Reading the title block
  • 2:48Distributing

Step 1 — Upload the revision

Take this part slowly the first time. SasCon checks the file against the project numbering rule before anything is published, so nothing you do here is visible to the team until the checks pass.

  1. 1Open Documents → Register and type the document number into the register search box.
  2. 2Select the row for the document, then choose Actions → Upload revision. If that option is greyed out, the document is on hold.
  3. 3Drag your file into the upload panel. SasCon reads the title block and fills in the revision letter and revision date where it can.
  4. 4Check the revision letter, revision date and status against the drawing itself, and correct anything the title block reader got wrong.
  5. 5Write a revision note saying what changed. One sentence is enough, and it saves the next person opening both drawings to find out.
  6. 6Select Upload. The file is scanned and validated, then published to the register.
Screenshot not uploaded yet
Figure 1 — The upload panel, with the revision letter and date read from the title block. Callouts: (1) File drop area, (2) Revision fields, (3) Revision note.
Nothing is sent yet
The revision stays in Pending while validation runs. You get a notification either way, and no one is emailed until you distribute it in step 2.
Publishing supersedes the previous revision
The earlier revision moves to Superseded and can no longer be issued. It stays in the revision history for audit, so nothing is lost — but you cannot reverse the supersede yourself.

Field reference

FieldRequiredWhat to enter
Document numberYesGenerated from the project numbering rule. Read-only once the document has been published.
RevisionYesLetters for design issues, numbers for construction issues. Follow whatever the previous revision used.
Revision dateYesThe date printed on the title block, not today’s date.
StatusYesPreliminary, For review, or For construction. Ask the project manager if you are unsure.
DisciplineYesDecides which distribution matrix SasCon suggests in step 2.
Revision noteNoStrongly recommended. Appears in the revision history and on the transmittal.

Step 2 — Distribute to the review team

Distributing creates a numbered transmittal. Recipients see the revision in their register straight away and get an email carrying your cover note.

  1. 1Open the published revision and select Distribute.
  2. 2Choose the saved distribution matrix for the discipline, or add companies and people by hand.
  3. 3Set what you need back — for information, for review, or for approval — and add a due date if a response is required.
  4. 4Write a short cover note and select Issue. Check the delivery log afterwards to confirm everyone received it.
Screenshot not uploaded yet
Figure 2 — Distribution with the structural review matrix selected and a due date set.